BOND UPDATE / Week of April 15, 2015

ASPHALT RECYCLE IN PLACE

Spring Valley Alley: Started laying asphalt Tuesday. Should be completed with the asphalt overlay by Wednesday.

Spur Trail: Equipment has been moved to Spur Trail and work will begin Monday 4/20 due to weather.

Next streets for Recycle in Place will be Lost Valley also Rockmartin and Chaparral west of Templeton Trail.

RESURFACING

Sundown from Longmeade to Josey and Birchlawn from Josey to Richland is scheduled for asphalt this week depending on the weather.

Repairs on Sundown from Josey to Richland should be complete within 2 weeks depending on the weather.

Golfing Green repairs from Webb Chapel to Longmeade and Golfing Green Cir. should be completed in 3 to 4 more weeks depending on the weather.

Next street for milling will be Onyx.